Scrum Master assessments may use practical team scenarios to explore facilitation and coaching. The fictional exercises below test how you support a Scrum Team, help remove impediments and encourage empirical improvement. They use Scrum accountabilities rather than assuming the Scrum Master directs the Developers’ work.
Preparing for a Scrum Master interview? Explore the guide to common interview questions from Interview Detectives for more worked examples and answer preparation.
Try each exercise before reading the answer. Allow around 15 to 20 minutes per task, unless your own assessment specifies a different time. All figures and organisations are illustrative.
Exercise 1: Respond to repeated unfinished Sprint work
Across the last four Sprints a team selected 30, 32, 28 and 30 story points of work. It completed 20, 22, 18 and 20 respectively. Developers report frequent unplanned requests. A manager wants the Scrum Master to enforce a target of 35 points.
Your task: Explain how you would facilitate a response.
Worked answer
The average selected work was 30 points and the average completed work was 20. This is useful information for the team to examine, but story points are a local estimation tool and should not become a productivity target. I would facilitate a discussion about the unplanned work and whether the Sprint Goal was achieved.
I would help the Developers explore capacity, interruptions and the size of the selected work. The Product Owner and Developers could discuss a more realistic forecast and how incoming requests affect the Sprint Goal. I would coach stakeholders on using the Product Owner to make priority decisions.
At the retrospective I would encourage the team to agree a specific experiment, such as making unplanned requests visible and reviewing their effect on the Sprint. We would inspect the result and adapt in the next retrospective.
What makes this effective: The response uses empirical evidence without turning estimates into individual performance measures.
Exercise 2: Facilitate a difficult Daily Scrum
The Daily Scrum has become a 40-minute meeting where each Developer reports to the Scrum Master. One Developer regularly raises a dependency, but the team rarely discusses it. The team is struggling to meet its Sprint Goal.
Your task: Describe how you would help improve the event.
Worked answer
I would discuss the purpose of the Daily Scrum with the Developers: inspecting progress towards the Sprint Goal and adapting the plan for the coming day. It is their 15-minute event. I would coach the team to use a format that helps them coordinate their work rather than report to me.
I would encourage the team to identify the work most relevant to the Sprint Goal and make dependencies visible. Longer problem-solving discussions could happen after the event with the relevant people. I would offer support in addressing impediments that the team cannot resolve itself.
I would ask the Developers to inspect whether the revised approach helps them coordinate and whether the dependency is being resolved. My role would be to support their ownership of the event.
What makes this effective: This restores the event’s purpose and protects the Developers’ accountability for their plan.
Exercise 3: Handle a mid-Sprint priority request
A senior stakeholder asks a Developer to stop working on the Sprint Goal and build an urgent dashboard. The Product Owner is unaware of the request. The stakeholder argues that the request must be completed this week.
Your task: Explain how you would respond.
Worked answer
I would bring the request to the Product Owner and help clarify its urgency and the value it would provide. I would coach the stakeholder on the agreed way to raise new work and explain how changing direction could affect the Sprint Goal.
The Product Owner and Developers can negotiate the Sprint Backlog as more is learned, provided the Sprint Goal remains protected. If the request can be accommodated without jeopardising the goal, they can agree how to proceed. If the goal has become obsolete, the Product Owner has authority to cancel the Sprint.
I would support a transparent conversation about the trade-off and help remove any organisational impediment that is causing recurring direct requests.
What makes this effective: The answer respects Scrum accountabilities and helps stakeholders make informed priority decisions.
Exercise 4: Run a retrospective that leads to improvement
The last three retrospectives produced several action items, but none were completed. Developers say the same problems keep returning and are losing confidence in the event.
Your task: Design the next retrospective.
Worked answer
I would review the previous actions with the team and explore why they were not completed. I would create space for quieter participants to contribute, using a short individual reflection before a group discussion if helpful.
I would help the team select one significant problem within its influence and agree an achievable improvement. For example, if code reviews are regularly delayed, the Developers might agree to review outstanding requests each day and measure how long they wait.
I would encourage the team to make the improvement visible in its work plan, with an agreed way to inspect progress. At the next retrospective we would assess whether it helped and decide how to adapt.
What makes this effective: The retrospective produces a concrete experiment with a way to learn from its result.
Prepare for the rest of your interview
Use our Scrum Master interview questions and sample answers to prepare examples from your own career. For other interview formats, see the job interview preparation guide.
Preparing for a Scrum Master interview? Explore the guide to common interview questions from Interview Detectives for more worked examples and answer preparation.